QX1201.1 (7/15/92) MIL-W-8604AER Requirements
Welding procedure specification (WPS) to be used for production parts against this contract per specification MIL-W-8604AER shall be forwarded to the address listed below at least ten (10) weeks in advance of production welding. The (WPS) shall include the approval signature of the authorized government representative and objective evidence that the tests specified in "section 4" of MIL-W-8604AER were satisfactorily completed.
General Dynamics Land Systems Division
Lima Assembly Tank Plant
1161 Buckeye Road
Lima, Oh 45804
Attn: Material Control Laboratories
|